
1. Context and Rationale
1.1. About SOS Children’s Villages Ethiopia
SOS Children’s Villages in Ethiopia is an International Non-governmental organization and a member of the SOS Children’s Villages International Federation. The organization started its humanitarian work in Ethiopia with the opening of its first Village in Mekelle, the Northern part of Ethiopia in 1974. Since then, it has expanded its programmes to different regions including Amhara, Oromia, Somali, Harari, Sidama, Southern Ethiopia, and South-Central Ethiopia regions and Addis Ababa. Through its unique family-based care model, the organization has provided a nurturing environment where children can flourish, grow, and realize their full potential. The programme also works with different youth empowerment initiatives, supporting young people to help them become productive and independent members of society. The family and community development programme has enabled many families in the communities to become sustainable and provide the necessary care for their children. Furthermore, SOS Children’s Villages in Ethiopia also provides humanitarian assistance interventions in cases of natural and human-made disasters, when the livelihoods of families and communities are disrupted. SOS CVE collaborates and partners with like-minded organizations, community structures, government entities, and relevant all in advocating for the fulfilment of the rights and needs of vulnerable children, young people and families.
SOS CV Ethiopia engages with a variety of community-managed organizations and local government authorities. It supports them in providing an enabling environment for the most vulnerable communities and families to access vital social services and protection whether in peaceful times or crises, to ensure care and protection for all children and youth living in their community
1.2. Description of Programme Location and Context
The SOS CVE Arbaminch Program location is the recent and newly established location under SOS Children’s Villages Ethiopia, founded in 2025 in response to the severe landslide and drought that affected the southern region and southern Oromia, Borena zone respectively. As an independent non-governmental organization focused on social development, we are dedicated to supporting vulnerable children. Currently, the program location (PL) runs two projects, which fall under one ion family strengthening, and humanitarian action programs.
The rational for the environmental impact assessment is to identify the impact of project intervention on the environment and the vice versa. The assessment also seeks to provide environmental risk information for the project team to develop mitigation mechanisms so that the impact of intervention on the environment will be compensated and relevant strategies will be developed accordingly.
The rational for baseline is to provide baseline information, assess the situation of the targeted communities before its implementation and set benchmarks and set target targets accordingly.
An Environmental Impact Assessment (EIA) is used to evaluate the potential environmental consequences of a proposed project or development. It helps decision-makers understand the likely impacts on the environment and human health before a project begins, enabling them to make informed decisions about whether to proceed and how to mitigate potential negative effects.
The project operation has been experienced recurrent environmental risks, the recent landslide is one of the indicators of environmental risks, causing families, children and elders displacement leading to complicated life in relocated areas where basic service was limited. The landslide happened in project operation areas degraded the land, affected farming activities, disrupted the existing social structures and complicated the service provided by the local government. EIA is most valuable when applied early in the planning process for a project as a support to decision making. It provides a means to identify the most environmentally suitable option at an early stage, the best practicable environmental option, and alternatives to the proposed initiative; and thus, avoid or minimise potentially damaging and costly negative impacts and maximise positive impacts. The finding of environmental impact assessment will be used to mitigate environmental impacts, design mitigation strategies and introduce safe programming
3.Objectives of the study
3.1 Overall objective:
This exercise has two overall objectives. The first objective related to Environmental Impact Assessment (EIA) which is intended to identify the impacts (both beneficial and adverse) of a proposed project activity. Often, the focus is dominantly environmental (biophysical); it also addresses social and economic aspects. It also aims to identify the most environmentally suitable option at an early stage, the best practicable environmental option, and alternatives to the proposed initiative; and thus, avoid or minimise potentially damaging and costly negative impacts and maximise positive impacts.
The second overall objective is related to baseline assessment which is intended to establish baseline values for key indicators, mentioned in the log frame.
3.2 Specific objectives:
The specific objectives of the environmental impact assessment (EIA) and baseline survey are:
3.3 Project out comes and outputs:
The Goal: Communities and institutions operate self-sustaining, resilient systems, with established financial, environmental, and service delivery capacities to manage future risks independently
The overall objective (OO) of the project is to: Enhance the resilience, food and nutrition security, and well-being of vulnerable populations in Geze Gofa Woreda by strengthening their ability to anticipate, absorb, adapt to, and recover from climate-related and other shocks through climate-resilient and low-carbon food systems, improved consumption of diverse, nutritious, and safe foods, and strengthened local institutions delivering health, nutrition, education, protection, and disaster risk management services.
Building on the above strategic orientations, the intervention will deliver the following interrelated outcomes and outputs:
Expected Outcome(E01): Early warning systems and community preparedness to anticipate and respond to natural and man-made hazards are strengthened in five target kebeles of Geze Gofa Woreda.
Outputs contributing to Expected Outcome(E01):
Expected Outcome(E02): Household and community resilience in five target kebeles is strengthened through integrated natural resource management and climate-resilient, agroecological, and nutrition-sensitive livelihood systems, supported by innovative, community-led financing and market integration mechanisms.
Outputs contributing to Expected Outcome(E02):
Expected Outcome(E03): Local systems for delivering integrated health, education, and protection services are strengthened to improve equitable access, quality, and accountability in five target kebeles of Geze Gofa Woreda.
Outputs contributing to Expected Outcome (EO3):
These outcomes and their respective outputs collectively contribute to the project’s overall objective and ensure that resilience is built not only at the household level, but also within community institutions, market systems, and governance structures, thereby ensuring sustainability and long-term impact.
The commissioned consultant should list out techniques of environmental impact assessment and baseline survey that can easily be used and adopted to the local context. The most recent and automated EIA tools like NEAT+ (Nexus Environment Assessment Tool plus) are recommended in this context. The baseline survey tools will be based on the project proposal to be shared with you upon award of the assignment.
Specifically, the EIA is limited to assessing the environmental impact pertaining to the proposed project intervention, environmental risks posing negative impact on the program activities and local communities. The baseline survey mainly focuses on assessing the situation of targeted communities’ food security, agriculture, livelihood, safety and protection before the project starts. Geographically, the project targeted five kebeles of Geze Gofa Woreda (Burda, Alagia Bola, Ala Galate, Amaro Shage, and Bedero Kota).
| Quantity |
Project total direct participants | 13,712 |
| |
Project indirect participants | 92,888 |
|
|
Project total participants | 106,600 |
5.Environmental Impact Assessment (EIA) and baseline survey methodology:
The consultant(s) must develop a strong data collection methodology for both EIA and baseline survey, ensuring the data's reliability and validity. A mixed-methods approach, combining quantitative and qualitative research methods, is recommended to produce the highest quality and most credible evidence. This study will collect data, disaggregated by sex, age, and disability, for the indicators listed in the result framework (the RF will be annexed for the winner consultant). The chosen methodology must be sensitive to the local context and ensure that all respondents, regardless of their background, have an equal opportunity to participate in EIA and baseline survey. Both the EIA and baseline should be designed to provide safe and inclusive spaces that encourage all participants to respond freely, irrespective of gender, age, disability, origin, or religious beliefs. As far as possible, the consultant should disaggregate data by sex, age, and disability while collecting and analysing data. Furthermore, the consultant should also clearly explain which questions will be answered using which methods. The Consultant should also ensure that the survey and qualitative methods (such as focus group discussion (FGD), key informant interview (KII) and group discussion with participants are representative of the project’s target groups.
5.1 Sampling
The consultant is required to propose statistically sound sampling strategies for both EIA and baseline survey to ensure representativeness. He/she is required to clearly state the sample size and the acceptable margin of error. The consultant will develop a detailed data analysis plan, outlining the statistical methods to be used for the quantitative data and the thematic analysis approach for the qualitative data. All data collection activities should be conducted following the highest ethical standards, ensuring informed consent, confidentiality, and the safety of all participants.
6.Work plan and expected deliverables
6.1 Work plan/timetable
Both the EIA and baseline survey tasks are expected to be finalized within 45 days After the contractual agreement is signed. The consultant is expected to develop her/his detailed work plan based on the following table.
Tasks (EIA and baseline survey) | Activities | Dates | Time frame | Location |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Deliverables:
The commissioned external consultant must deliver the EIA and baseline survey findings within 45 days of the contract signed. Based on the work plan, SOS Children’s Villages of project intervention programme locations Arbaminch and the national office MEAL and Humanitarian Response program team expect the following deliverables:
Qualification of the Researcher/Research Team
Report criteria:
The reporting criteria for both EIA and baseline survey task shall be in line with the SOS Children’s Villages Ethiopia result based management (RBM) toolkit and should be shared with the winner consultant along with the data review process and/or for the preparation of the inception report.
Child safeguarding and ethical issues.
SOS Children’s Villages is committed to ensuring that all assessment, research, evaluation and data collection processes (i.e. evidence-generating activities) undertaken by SOS Children’s Villages and its partners are ethical and respect child safeguarding policy and procedure.
The consultant must respect the rights, dignity and protection of children and other vulnerable population groups and should ensure special protection for children and other vulnerable groups during any data-generating activities to minimize any potential risks. Any assessment, research, evaluation and data collection SOS Children’s Villages is directly carrying out or is involved in as a partner.
Ethical practices need to be ensured in the following circumstances:
Hence, relevant Coordinator in SOS Children’s Village Arbaminch and Humanitarian Program department will ensure that any researchers, evaluators and data collectors should receive awareness training on, sign and adhere to SOS Children’s Villages core policies:
Obtaining consent from research participants is central to the research relationship and signals respect for the research participant's dignity, their capability to express their views and their right to have these heard in matters that affect them. Informed consent is an explicit agreement which requires participants to be informed about and understand the research/assessment. This must be given voluntarily and be renegotiable, so that participants may withdraw at any stage of the research process.
Logistical arrangements:
The awarded consultant shall show feasible logistical arrangements for the assignment as part of the technical proposal. National or location-level staff (SOS CVE) will be available to help organize the interviews including contacting SOS CVE, announcing and local preparation of evaluation, and linking to community duty bearers and national authorities if required.
11.Duration of the contract and terms of payment
Duration of contract: the contract is effective from the moment it was signed until the acceptance of work by the SOS Children’s Villages in Ethiopia management team.
Payment will be made only upon SOS Children’s Villages' acceptance of the work performed in accordance with the above-described deliverables. Payment will be affected by bank transfer in the currency of birr. The details of the payment will be mentioned below
Notice of delay
Shall the successful bidder encounter a delay in the performance of the contract which may be excusable under unavoidable circumstances; the contractor shall notify SOS Children’s Villages in writing about the causes of any such delays within one (1) week from the beginning of the delay.
After receipt of the Contractor's notice of delay, SOS Children’s Villages in Ethiopia shall analyse the facts and extent of the delay and extend the time for performance when in its judgment the facts justify such an extension.
Copyright and other proprietary rights:
SOS Children’s Villages shall be entitled to all intellectual property and other proprietary rights including, but not limited to, copyrights, and trademarks, with regard to products, processes, inventions, ideas, know-how, or documents and other materials which the Contractor has developed for SOS Children’s Villages under the Contract and which bear a direct relation to or are produced or prepared or collected in consequence of, or during the course of, the performance of the Contract. The Contractor acknowledges and agrees that such products, documents, and other materials constitute works made for hire for SOS Children’s Villages.
All materials: interviews, reports, recommendations, and all other data compiled by or received by the Contractor under the Contract shall be the property of SOS Children’s Villages and shall be treated as confidential and shall be delivered only to SOS Children’s Villages authorized officials on completion of work under the Contract. The external consultant is obliged to hand over all raw data collected during the assessment to SOS Children’s Villages in Ethiopia.
Termination:
The termination of the service agreement for the assignment will be in accordance with the contractual agreement to be included at the formal agreement's actual signing.
Annex:
The winning consultancy firm will be shared with the following documents.
Interested vendors should submit a complete proposal comprising:
Submission Details